Rebuild steps - all are VMware servers, so we can fall back easily:
- Copy a backup of the CLICK sites off to an archive - 30 to 60 minutes
- deactivate the old VM
- Create the new VM with the same name and IP - Tom B - 2 - 2.5 hours - this can be done aheady of time but not start it until the old one is deactivated.
- Install SQL Server + SP3 + BOL - 1 hour +
- Install CLICK - 1 hour - 5.5.3 plus the framework patches 01, 05, and 06
- Copy the sites back - 30 - 60 minutes
- Create and load the CLICK sites - 60 minutes (can overlap a bit with 6)
- test - if fails then Tom B plus Net Ops needs to restore the old VMware site.On TRAIN the training site will be restored from PROD, not the old one (better keep a copy just in case).